Delivered project · Penthouse refit (existing apartment)
Trasacco Penthouse Refit — Luxury 3-bedroom refit, 380 m²
Luxury · 380 m² · 16 weeks

At a glance
| Location | Type | Tier | Area | Duration | Scope of supply |
|---|---|---|---|---|---|
| Trasacco, Accra | 3-bedroom penthouse refit | Luxury | 380 m² | 16 weeks | Entrance door, custom kitchen & wardrobes, interior doors, sanitaryware & hardware, lighting and smart-home controls, tiles & flooring, furniture |
The brief
An existing three-bedroom penthouse in Trasacco, around ten years old and fully fitted, which the owner wanted stripped back and refinished to a higher standard rather than patched. The scope covered everything visible: a new entrance door, floors, interior doors, a custom kitchen, a master suite with dressing room and bathroom, two further bathrooms, furniture and a full lighting and smart-home scheme, all at the Luxury tier.
What we supplied
- Entrance door — Luxury tier
- Custom kitchen, dressing room and wardrobes — Luxury tier
- Interior doors — Luxury tier
- Sanitaryware and bathroom fittings — Luxury tier
- Tiles and flooring — Luxury tier
- Lighting and smart-home controls — Luxury tier
- Furniture and upholstery — Luxury tier
How it was delivered (indicative)
| Stage | What happened | Week |
|---|---|---|
| 1. Measurement | Survey of existing penthouse, strip-out scope agreed | 1–2 |
| 2. Design | Luxury scheme, material samples, itemised budget | 2–4 |
| 3. Sourcing | Orders placed; kitchen, dressing room and entrance door into production | 5–9 |
| 4. QC & consolidation | Factory inspections, crating, consolidation in Foshan | 9–10 |
| 5. Shipment & clearance | Sea freight to Tema, clearance, delivery to building | 10–13 |
| 6. Installation | Strip-out complete, supervised installation, snagging, handover | 13–16 |
Challenges and how we handled them
- Strip-out in an occupied building. Typical for a refit, removal of the old fit-out had to follow building rules on noise, hours and waste. The strip-out was programmed during the shipping window so the apartment was clear when the container landed.
- Large items and lift access. The entrance door and some surface panels do not fit a standard lift. Item sizes were checked against the lift and stair at survey stage and large panels were cut to manageable sizes in Foshan.
- Longer production. Custom joinery and Luxury-tier finishes extend factory lead times. The 16-week programme allowed for this rather than compressing it.
Result
A ten-year-old penthouse refitted to a Luxury standard in 16 weeks: a new entrance door and floors, a custom kitchen, a complete master suite, three bathrooms, furniture, and lighting with smart-home control throughout.
Next step
Refitting an existing apartment in Accra? Start with an estimate at /estimator, or message the Accra office on WhatsApp +233 59 247 0446.
Related: Apartment packages · How Long to Finish a House in Ghana: Stage Timeline · Contact